Direct answer: the UK CBAM starts on 1 January 2027 and puts a carbon price on imports of five groups of "CBAM goods": aluminium, cement, fertiliser, hydrogen, and iron and steel. The liable person is the UK importer/customs declarant, not the Chinese exporter, but exporters must give UK customers verifiable emissions-intensity data; otherwise the importer can only use the government's default values (DVs). The registration threshold is £50,000 (forward-looking 30 days or backward-looking 12 months). Registration opens on 1 January 2028, with a first-year deadline of 31 January 2028. The first accounting period is calendar-year 2027, with the return and payment due by 31 May 2028; quarterly periods follow. CBAM initially covers direct emissions (including relevant precursors); indirect emissions are delayed until 2029 at the earliest. The government has published default values and illustrative rates: DVs by 8-digit CN code, and illustrative rates of about £9.69 for steel, £9.79 for aluminium, £8.78 for cement, £1.45 for fertiliser and £9.24 for hydrogen per tCO2e. These are "illustrative, based on current data", not final rates; the first quarterly rates will be published before 2027 and updated quarterly.

This guide is for Chinese manufacturers and traders exporting these goods to the UK, UK importers/customs brokers, emissions verifiers and supply-chain teams. It separates "who pays, how much, which data, when to register/file, and what exporters should prepare now." Sources are the GOV.UK CBAM policy summary (updated 2 November 2026), the CBAM collection (updated 9 September 2026), the default-values pages (published 16 October 2026) and the illustrative rates/worked example (published 16 October 2026), all accessed 8 November 2026. Official facts, editorial calculations and items to confirm are kept separate. This is not tax or legal advice.

Three rules to remember

(1) From 1 January 2027, UK importers pay CBAM on aluminium, cement, fertiliser, hydrogen and steel; Chinese exporters do not pay the tax directly, but must supply verifiable emissions data so customers pay less. (2) Actual data must be verified by a qualifying verifier (site visit, 5% materiality threshold); a return filed with default values cannot later be amended to actual data. (3) The first return is due 31 May 2028, but records must start on 1 January 2027; retrofitting data at the end usually fails.

Timeline: starts 2027, registration and first return 2028

The legal basis is the Finance Act 2026, supported by emissions/verification regulations and force-of-law notices progressed in 2026. The policy summary states: liability starts 1 January 2027; registration opens 1 January 2028; calendar-year 2027 is the first accounting period; the first return is due 31 May 2028. That means goods imported in 2027 are not immediately reported, but customs, weight, emissions-intensity and carbon-price evidence must be retained from day one. Reconstructing verifiable data in 2028 is usually not possible.

DateEventWhat it means
2026Finance Act 2026, secondary legislation, DVs and illustrative rates publishedScope, rate methodology, DVs and verification rules set
1 Jan 2027CBAM startsUK importers begin to incur liability; exporters begin to supply data
Calendar 2027First accounting period (annual)Keep records by quarter/consignment; prepare first return
1 Jan 2028Registration opensImporters above the £50,000 threshold register
31 Jan 2028First-year registration deadlineLatest date for first-year importers to register
31 May 2028First return and payment due2027 CBAM return/payment
From 2028Quarterly returnsFile/pay by the official quarterly deadlines
2029 earliestIndirect emissions may be includedElectricity/indirect emissions not in the 2027 scope

Sources: GOV.UK "Carbon Border Adjustment Mechanism (CBAM): Policy summary" (updated 2 November 2026) and the CBAM collection (updated 9 September 2026). Editorial summary; dates/transitional arrangements follow the latest legislation and HMRC guidance.

Scope: five sectors, CN codes, scrap excluded

CBAM covers specified CBAM goods imported into the UK (including Northern Ireland), identified by 8-digit CN code, in aluminium, cement, fertiliser, hydrogen, and iron and steel. The government confirms glass and ceramics are not in the 2027 scope and aluminium/steel scrap is excluded by the relevant CN codes; goods entering the UK from the Crown Dependencies, Overseas Territories and the UK Continental Shelf are also subject. It applies per consignment by CN code, weight and emissions intensity, not per company or brand. The exporter's first step is mapping each product to the UK Tariff's 8-digit CN code, not just "aluminium" or "steel".

SectorExample CN / productDefault value (tCO2e/t)Note
Aluminium76011090 unwrought non-alloy aluminium2.136Slabs 76011010: 2.058
Aluminium76012040 unwrought alloy billets2.030Alloy slabs 76012030: 2.038
Aluminium76041010 non-alloy bars/rods/profiles3.021Hollow alloy profiles 76042100: 3.894
Steel72083800 hot-rolled coil (>=3mm and <4.75mm)3.77872083700: 3.314
Steel72142000 ribbed rebar/coils3.04072149910 smooth rebar: 2.562
Steel72011011 non-alloy pig iron1.33172011090: 2.698
Cement25231000 cement clinkers1.43325232900 Portland cement: 1.375
Fertiliser31021019 urea (>45% N)1.39231021090: 1.773
Hydrogen28041000 hydrogenSee official DV pageCheck the latest value by CN code

Sources: GOV.UK default-values pages (Aluminium/Cement/Fertilisers/Iron and steel, published 16 October 2026). Only examples are shown; use the official page for the full 8-digit CN list. DVs may be updated; use the version in force at filing.

Calculation: CBAM charge minus Carbon Price Relief

The liability formula is: CBAM charge = imported embodied emissions x CBAM rate; Carbon Price Relief (CPR) = relevant embodied emissions x effective carbon price; liability = charge - CPR. Embodied emissions = emissions intensity (tCO2e/t) x weight (t); complex goods also include relevant precursor emissions. Emissions intensity can come from verified actual data or government DVs. Note: if the final good uses DVs, precursors cannot use actual data; if the final good uses actual data, precursors may use actual or DVs.

ComponentCalculationData source/caveat
CBAM chargeEmbodied emissions x CBAM rateRate by sector, published quarterly
Embodied emissionsIntensity (tCO2e/t) x weight (t)Verified actual or DV; includes relevant precursors
Carbon Price ReliefRelevant emissions x effective carbon priceEvidence of deductible carbon price in origin country
LiabilityCharge - CPRCPR cannot be negative; retain evidence
WeightDeclared in kg; HMRC converts to tonnesNet weight by CN code/consignment
PrecursorsPrecursor weight x precursor intensity/DVComplex goods; see System Boundaries

Sources: GOV.UK CBAM policy summary section 5 (updated 2 November 2026) and the default-values pages. Editorial summary; qualifying carbon prices, evidence and verification follow official guidance.

Illustrative rates and 1,000-tonne examples: scale only, not final tax

On 16 October 2026 GOV.UK published "illustrative rates": based on the Q3 2026 average UK ETS price and preliminary baseline data, the 2027 rates would be about £9.69 for steel, £9.79 for aluminium, £8.78 for cement, £1.45 for fertiliser and £9.24 for hydrogen per tCO2e. The government explicitly says these are not forecasts or final rates; the first quarterly rates will be published before 2027 and updated quarterly. Using these and DVs gives a quick order of magnitude for 1,000 tonnes: aluminium about £20,911, steel about £36,609, cement about £12,582 and urea about £2,018; actual liability also subtracts CPR and will change with rates/DVs.

Sector / exampleIllustrative rate (£/tCO2e)DV (tCO2e/t)1,000 t emissions (tCO2e)Illustrative liability (£)
Aluminium 760110909.792.1362,13620,911.44
Steel 720838009.693.7783,77836,608.82
Cement 252310008.781.4331,43312,581.74
Urea 310210191.451.3921,3922,018.40
Hydrogen 280410009.24See official DV--

Editorial calculation: 1,000 t x DV x illustrative rate; excludes Carbon Price Relief, FX, tax, monitoring/verification cost and final rate changes. Illustrative rates come from GOV.UK "Illustrative CBAM rates (and worked example)" (16 October 2026); the government states the data may change, the first quarterly rates will be published before 2027 and updated quarterly, and the figures are not final liability or forecasts.

How the rate is built: UK ETS average x free-allocation phase-out

CBAM has no single fixed rate. It is calculated by sector and quarter as: average UK ETS price x [1 - (baseline free-allocation percentage x free-allocation phase-out factor)]. The official cement example uses the Q3 2026 average of £58.15, a cement baseline free-allocation percentage of 87.1% and a 2027 phase-out factor of 97.5%, giving £8.78/tCO2e. As free allowances are phased out, the CBAM rate changes over time; do not use the 2027 illustrative rate as a 2030 budget.

InputCement exampleNote
Average UK ETS price£58.15/tCO2e (Q3 2026)Previous quarter's auction average; latest auction quarter if none
Baseline free-allocation percentage87.1%Sector sub-installation free allowances/direct emissions
Free-allocation phase-out factor97.5% (2027)Same across the five CBAM sectors
Rate formula£58.15 x [1 - (87.1% x 97.5%)]Official example: £8.78/tCO2e
Update frequencyQuarterlyFirst quarterly rate published before 2027

Source: GOV.UK "Illustrative CBAM rates (and worked example)" (16 October 2026). The table reproduces the official cement example; other sectors use their own baseline free-allocation percentage and the same phase-out factor. Illustrative data may change; final rates follow the first quarterly publication and updates.

Actual data vs default values: how to choose

DVs let an importer file without installation data, but at a cost: a return filed with DVs cannot later be amended to actual data; DVs are government averages and may be above or below your actual intensity. Actual data requires monitoring, verification, a site visit and an evidence chain; it costs money, but exporters with low intensity and large volumes usually benefit. High-intensity or small-volume exporters may find DVs simpler. This is not a "compliant/non-compliant" choice but a cost/data/customer-contract trade-off, and it should be decided with the UK importer.

DimensionVerified actual dataDefault values (DVs)
Data requirementsMonitoring plan, activity data, emission factors, evidenceLook up official DV by CN code; no installation data
VerificationQualifying verifier, site visit, 5% materialityNo verification
Post-filing correctionErrors can be corrected within 3 yearsCannot switch to actual data
Liability impactLower if actual intensity is lowGovernment average; may be higher or lower
Cost/timeMonitoring, verification, travel, staffLow upfront cost, but possibly overpayment
Customer/contractUK importer may prefer locked actual dataCustomer may ask for price cuts or data later

Editorial summary, not official advice; eligibility, verification and filing rules follow GOV.UK guidance and HMRC requirements. Verification fees must be quoted by a qualifying verifier; this article does not quote them.

Registration, returns, records and penalties

UK importers above the £50,000 threshold must register. The threshold uses two tests: expected imports over the next 30 days, or actual imports over the preceding 12 months; meeting either triggers registration from the earlier date. Registration requires name/address/business type/EORI/VAT/trigger date/estimated 12-month weight by sector. Returns report each consignment by 8-digit CN code, net weight (kg), emissions intensity, carbon price paid, quarter and country of origin; records must be kept for 6 years; errors can be corrected within 3 years. HMRC can assess tax, compulsorily register and penalise failure to register/file/pay, errors and failure to comply with information notices.

StepRequirementEvidence/caveat
Registration threshold£50,000; forward 30 days or backward 12 monthsGoods value follows customs valuation
Registration timingOpens 1 January 2028; first-year deadline 31 January 2028Government Gateway; EORI/VAT
First return/paymentCalendar 2027; due 31 May 2028Quarterly thereafter
Return contentCN code, net kg, intensity, carbon price, quarter, originEach consignment separately
Record retention6 years after the accounting periodCustoms declarations, bills of lading, commercial documents, valuation evidence
Correction/repaymentWithin 3 years after the return periodRetain evidence; HMRC may check
PenaltiesFailure to register/file/pay, errors, non-cooperationHMRC assessment, compulsory registration, criminal provisions

Sources: GOV.UK CBAM policy summary sections 6-9 (updated 2 November 2026). Editorial summary; threshold tests, valuation, return fields and penalties follow the latest legislation/HMRC guidance.

Exporter 90-day readiness checklist

Chinese exporters are not the CBAM taxpayer, but they are the data source. Use the first 90 days to connect product CN codes, UK customers/importers, DVs, actual emissions data, verifiers, contract terms and record retention. The order is: map, compare with DVs, choose actual/default, find a verifier, update contracts/systems, rehearse filing.

PhaseActionOutput
Weeks 1-2Map each UK-bound product to its 8-digit CN code; confirm CBAM goods/scrap exclusionsProduct-CN list, scope conclusion
Weeks 2-3Look up the official DV for each CN code and estimate the customer's potential liabilityDV comparison, order-of-magnitude estimate
Weeks 3-5Inventory monitoring data/emission factors; compare actual intensity with DVData gaps, priorities
Weeks 5-7Decide actual verification vs DVs; contact qualifying verifiers for quotes/schedulingVerification plan, budget
Weeks 6-8Agree data format, filing responsibility and price-adjustment/indemnity clauses with the UK importerContract annex, SOP
Weeks 8-10Build consignment-level records: CN, net weight, intensity, carbon price, origin, customs declarationData dictionary, ledger
Weeks 10-12Run a mock return/customer reconciliation and close gapsMock return, remediation list

Editorial readiness advice, not an official template; monitoring, verification, filing and contract arrangements follow GOV.UK guidance, HMRC requirements and professional advice.

FAQ

When does the UK CBAM start?

It starts on 1 January 2027 for CBAM goods imported into the UK in aluminium, cement, fertiliser, hydrogen and iron/steel. The first accounting period is calendar 2027; the first return/payment is due 31 May 2028, and registration opens 1 January 2028.

Who pays CBAM? Does the Chinese exporter pay?

The liable person is the UK importer/customs declarant (or the person on whose behalf the declaration is made), not the Chinese exporter. The exporter must give the UK customer verifiable emissions-intensity data; otherwise the customer uses DVs, may pay more and cannot switch to actual data later.

Which products are covered?

Aluminium, cement, fertiliser, hydrogen, and iron and steel, determined by 8-digit CN code. Glass and ceramics are not in the 2027 scope; aluminium/steel scrap is excluded by the relevant CN codes. Check the official Annex/UK Tariff.

Should we use default values or actual data?

Actual data requires monitoring, verification and a site visit, but can significantly reduce liability when intensity is low and volumes are large. DVs have low upfront cost but cannot be replaced by actual data after filing. Decide based on intensity, volume, customer requirements and verification cost.

What is the CBAM rate?

There is no single fixed rate; it is calculated by sector/quarter from the UK ETS average and free-allocation phase-out. The 16 October 2026 illustrative rates were about £9.69 steel, £9.79 aluminium, £8.78 cement, £1.45 fertiliser and £9.24 hydrogen per tCO2e, but the government says they are not final; the first quarterly rates will be published before 2027 and updated quarterly.

Are indirect emissions included?

From 2027 only direct emissions (including relevant precursors) are covered; indirect emissions are delayed until 2029 at the earliest. Electricity/indirect emissions are not in the first period, but this may change and should be monitored.

What records must be kept?

CN code, import date, value, net weight, emissions intensity, carbon price paid, country of origin, customs declarations/bills of lading/commercial documents, etc., for 6 years after the accounting period. Errors can be corrected within 3 years.

What happens if we do not register or file?

HMRC can assess the tax, compulsorily register the business and penalise failure to register, file or pay, errors and non-cooperation with information notices; fraudulent evasion or deliberate misstatement can also attract criminal provisions. Check the legislation/HMRC guidance for details.

Research method and limitations

This article separates "official facts" from "editorial calculations." The start date, five sectors, CN scope, £50,000 threshold, registration/filing/payment timetable, 6-year retention, penalties, direct emissions/precursors and actual-vs-DV rules come from the GOV.UK "CBAM: Policy summary" (updated 2 November 2026) and the CBAM collection. CN-level default values come from the GOV.UK default-values pages (published 16 October 2026). Illustrative rates, the cement rate formula and the worked example come from GOV.UK "Illustrative CBAM rates (and worked example)" (published 16 October 2026). The 1,000-tonne liability estimates, 90-day checklist and actual-vs-DV framework are editorial.

Eight limitations: (1) this is not tax or legal advice; (2) illustrative rates are not final, and the first quarterly rates/updates are not yet published; (3) only example CN codes are covered, not all CBAM goods/precursors; (4) Carbon Price Relief, FX, verification/monitoring cost and contract price adjustments are excluded; (5) the latest UK Tariff/Annex CN changes are not checked line by line; (6) Northern Ireland/Crown Dependencies/special customs procedures are not fully covered; (7) EU CBAM/UK CBAM mutual recognition or differences are not assessed; (8) policy/guidance may change, so recheck the official pages before publishing or transacting.

Sources and basis

  • GOV.UK, Carbon Border Adjustment Mechanism (CBAM): Policy summary (updated 2 November 2026): gov.uk/.../cbam-policy-summary. Scope, tax point, liability, registration/filing/records/penalties, £50,000 threshold, timetable. Accessed 8 November 2026.
  • GOV.UK, Prepare for the Carbon Border Adjustment Mechanism (CBAM) (updated 9 September 2026): gov.uk/government/collections/carbon-border-adjustment-mechanism. Registration, records, emissions monitoring and verification entry points. Accessed 8 November 2026.
  • GOV.UK, Check the default values for CBAM (published 16 October 2026): gov.uk/.../check-the-default-values-for-cbam. Aluminium/cement/fertiliser/hydrogen/steel DVs by CN code. Accessed 8 November 2026.
  • GOV.UK, Illustrative CBAM rates (and worked example) (published 16 October 2026): gov.uk/.../illustrative-cbam-rates. Illustrative rates, cement rate formula/example, quarterly update. Accessed 8 November 2026.

Data cut-off 8 November 2026; rates/default values/scope follow the latest GOV.UK pages and HMRC guidance; this is not tax, legal or procurement advice.

Turn UK CBAM CN codes, default values, verification data and returns into a checkable list

Bring UK-bound products/CN codes, customers/importers, emissions data, verification arrangements, contracts and record processes; we turn UK CBAM readiness into a checkable list.

Book a UK CBAM review