Direct answer: A master-data migration/cleansing project acceptance page is not a line saying "data migrated, system live". The page should state: project scope and goals (supplier/material/price/contract/category/organisation/customer/bank domains, source/target systems, in-scope/out-of-scope, success criteria, data volume, cutover window); current-state inventory and data profiling (source list, completeness/duplicates/format/relationships, owner/steward, retention/archive); mapping and cleansing rules (source-to-target field mapping, coding/naming/classification/unit/currency/tax code, deduplication/merge, defaults/exceptions, approval, audit trail); trial migration and reconciliation (sample/full, quantity/amount/status reconciliation, issue log, fix/re-run, sign-off); cutover/rollback/post-go-live (freeze, sequence, rollback, parallel run, go-live checks, hypercare); public boundary. On the rules: MOF Internal Control Application Guideline No. 18 (Information Systems) requires system development, change, operation, security and data controls; No. 7 (Procurement) requires procurement records/traceability and supplier/price/contract controls; No. 8 (Asset Management) requires inventory records/stock reconciliation/count. This article is current to 2026-11-10 and is a summary of public rules and page method, not data-governance/IT-audit advice; the company's master-data policy, migration plan, system configuration and data standards control.

This article is for procurement, IT, finance, internal-control, audit, data-governance and website teams at equipment, electronics, automotive-parts, medical-device, hardware, chemical, packaging and export manufacturers in Changzhou and nearby. It covers how to write and accept a master-data migration/cleansing project acceptance page. The usual gap is "unclear scope, source data not inventoried, arbitrary mapping, cleansing rules without approval, trial migration without reconciliation, cutover without rollback, no post-go-live ownership", ending with a page that only says "data migrated, system live", while reconciliation/reporting/audit still disagree.

Three things to remember first

First define scope and success criteria: which domains, from where to where, how much data, when to cut over. Then profile and map: source issues, field mapping, cleansing/dedup rules, approval/trail. Finally trial-migrate and reconcile: sample/full, quantity/amount/status, issue closure, cutover/rollback/go-live checks. "Data migrated" is not enough.

How does this page relate to master-data quality, ERP/SRM implementation, supplier portal, inventory count and information-security pages?

The migration/cleansing project page answers "what this project migrates, how to map/cleanse, how to trial/reconcile, how to cut over/roll back"; the master-data quality page answers "ongoing domains/coding/governance/quality metrics"; the ERP/SRM implementation page answers "system scope/process/interfaces/go-live"; the supplier portal/SRM page answers "registration/RFQ/order/ASN"; the inventory-count page answers "count/variance/stock reconciliation"; the information-security page answers "classification/access/transmission/incidents". The migration project is the main page for "one-time delivery" and cannot be replaced by an ongoing master-data quality page.

Common breaks: scope creep/missing domains; source data not inventoried; arbitrary mapping; cleansing rules without approval; direct deletion of duplicates; trial migration without reconciliation; issues not closed; cutover without rollback; no post-go-live checks; missing permissions/audit; data/privacy leakage. The page separates "scope—profiling—mapping/cleansing—trial/reconciliation—cutover/rollback—post-go-live—public boundary" so procurement/IT/finance/internal-control/audit/data governance share one vocabulary.

PageQuestion it answersKey contentCannot replace
Migration/cleansingWhat to migrate/how to map/cut overScope, profiling, mapping, trial, cutoverOngoing data quality
Master-data qualityDomains/coding/governance/metricsStandards, owner, metrics, auditProject delivery
ERP/SRM implementationSystem scope/process/interfaces/go-liveModules, process, interfaces, trainingData cleansing/reconciliation
Supplier portalRegistration/RFQ/order/ASNAccount, order, ASNHistorical data migration
Inventory countCount/variance/reconciliationCount, variance, adjustmentMaster-data mapping
Information securityClassification/access/transmission/incidentsPermissions, encryption, incidentsData quality/reconciliation

Page relationships are editorial; the company's master-data policy, migration plan and system configuration control.

How should project scope, goals and success criteria be accepted?

Scope should state at least: data domains (supplier/material/price/contract/category/organisation/cost centre/customer/bank/payment terms/tax code); source systems (ERP/SRM/MDM/Excel/legacy) → target system; in-scope/out-of-scope (historical years, inactive data, attachments/documents); data volume (rows/attachments/interfaces); cutover window/downtime; success criteria (quantity/amount/quality/reconciliation variance/go-live date). Goals should be verifiable: e.g. "supplier/material master data 100% migrated, key-field completeness ≥X, duplicate rate ≤Y, quantity/amount reconciliation variance = 0, trial migration signed off"; specific values are company-defined. The project should also state roles (business owner, data steward, IT, supplier), plan/milestones, risks/dependencies.

Acceptance checks: domain list; source/target; in/out of scope; data volume; success criteria; roles; plan; risks. Common gaps: scope creep; missing domains; unclear history/inactive; vague success criteria; unclear roles.

ElementWhat to writeEvidenceCommon gap
Data domainsSupplier/material/price/contract/category/organisation/customer/bankListMissing domain
Source/targetERP/SRM/MDM/Excel/legacy → targetArchitectureUnclear source
In/out of scopeHistorical years/inactive/attachments/documentsScope noteCreep
Data volumeRows/attachments/interfaces/incrementalStatisticsEstimate
Success criteriaQuantity/amount/quality/variance/dateMetricsVague
RolesBusiness owner/steward/IT/supplierAppointmentUnclear
PlanMilestones/dependencies/windowPlanNo milestones
RisksData/system/resource/complianceListNot assessed

Scope/goals are editorial; the migration plan, master-data policy and project charter control.

How should current-state inventory and data profiling be accepted?

Inventory should state at least: source system/table/field/rows/owner; data dictionary/field meaning/type/length/required/enumeration; data-quality profiling (completeness/uniqueness/format/range/relationships/timeliness); duplicates/aliases/one material multiple codes/one code multiple materials; unit/currency/tax code/organisation mapping; attachments/documents/images; history/inactive/archive; permissions/sensitive data. Profiling output: issue list/samples/impact/priority/recommendation, confirmed by business owner/steward. Guideline No. 7 requires procurement records/traceability; No. 8 requires inventory records/stock reconciliation; No. 18 requires system data controls. Profiling is not just running a script; it needs business confirmation and remediation priority.

Acceptance checks: source list/dictionary; rows; quality dimensions; duplicates/aliases; unit/currency/tax; attachments; history/inactive; sensitive data; issue list. Common gaps: no dictionary; no profiling; duplicates unclear; units/currencies mixed; sensitive data unidentified.

ItemWhat to writeEvidenceCommon gap
Source listSystem/table/field/rows/ownerListIncomplete
DictionaryMeaning/type/length/required/enumerationDictionaryNo dictionary
Quality profilingCompleteness/uniqueness/format/range/relationships/timelinessReportNo profiling
Duplicates/aliasesDuplicates/aliases/one-material-multiple-codesListUnclear
Unit/currency/taxUnit/currency/tax code/organisation mappingCrosswalkMixed
Attachments/documentsAttachments/images/documents/pathsListMissing
History/inactiveHistory/inactive/archive/retentionRuleMigrate all
Sensitive dataBank/personal data/permissionsClassificationUnidentified

Inventory/profiling are editorial; the data standards, system dictionary and migration plan control.

How should mapping and cleansing rules be accepted?

Mapping should state at least: source field → target field, transformation rules (code/name/classification/unit/currency/tax code/date/status), required/default/exception, value mapping table, ID mapping (old ID → new ID), relationships/hierarchy (supplier-bank, material-BOM, price-contract). Cleansing: standardisation/trim/case/unit conversion/currency/tax code; deduplication/merge (rules, master record, impact, history/audit); missing/exception handling (fill/default/reject); approval (business owner/steward/data governance); trail (rule version/approval/execution log); rollback/re-run. Merging must not delete directly; keep old IDs/mapping/history. Guideline No. 18 requires system change/data controls; No. 7 requires procurement record traceability.

Acceptance checks: field mapping; transformation rules; default/exception; value mapping; ID mapping; relationships; dedup/merge; missing/exception; approval; trail; rollback. Common gaps: arbitrary mapping; no value mapping; direct deletion; no approval; no old-ID mapping; unclear rule version.

ItemWhat to writeEvidenceCommon gap
Field mappingSource→target/type/lengthMapping sheetArbitrary
TransformationCode/name/classification/unit/currency/tax/date/statusRuleInconsistent
Default/exceptionRequired/default/exception/rejectRuleNo exception
Value mappingEnumeration/code/unit/currency/taxCrosswalkNo mapping
ID mappingOld ID→new ID/relationship/hierarchyMapping sheetBroken link
Dedup/mergeRule/master record/impact/history/auditRecordDirect delete
ApprovalBusiness owner/steward/governanceApprovalNo approval
Trail/rollbackRule version/log/re-run/rollbackLogNo version

Mapping/cleansing are editorial; the data standards, migration plan and system configuration control.

How should trial migration and reconciliation be accepted?

Trial migration should state at least: environment (test/pre-production/production), rounds, scope (sample/full), data volume, time window; execution (extract/transform/load/validate); reconciliation (source/target rows, key fields, amount/quantity, status, relationships/hierarchy, attachments); variance categories (missing/duplicate/error/truncation/coding/amount) and thresholds; issue log (finding/owner/fix/re-run/recheck/close); business sample confirmation (procurement/finance/warehouse/quality); sign-off/production admission. Guideline No. 7 requires records/traceability; No. 8 requires stock reconciliation; No. 18 requires system change/data controls. Trial migration is not "the script ran"; it needs a checkable reconciliation report and business sign-off.

Acceptance checks: environment; rounds; scope; data volume; execution; reconciliation; variance; log; fix/re-run; business sign-off. Common gaps: one run only; too small a sample; no reconciliation; variances not closed; no business sign-off.

ItemWhat to writeEvidenceCommon gap
EnvironmentTest/pre-production/productionRecordDirect production
Rounds/scopeSample/full/data volume/windowPlanOne run
ExecutionExtract/transform/load/validateLogNo log
ReconciliationRows/fields/amount/quantity/status/relationships/attachmentsStatementNo reconciliation
VarianceCategory/threshold/samplesReportNot categorised
LogFinding/owner/fix/re-run/recheck/closeLogNo closure
Business sampleProcurement/finance/warehouse/quality confirmationRecordNo confirmation
Sign-offProduction admission/conditions/open itemsSign-offNo sign-off

Trial/reconciliation are editorial; the migration plan, data standards and system capability control.

How should cutover, rollback and post-go-live be accepted?

Cutover should state at least: cutover window/downtime; freeze (legacy writes/interfaces/approvals); sequence (master data → price/contract → inventory/opening → interfaces); owners/contacts; checkpoints/Go-No-Go; rollback conditions/steps/window/data recovery; parallel run/dual run (if applicable); go-live checks (quantity/amount/status/interfaces/reports/permissions); hypercare (days/response/severity); open items/remediation. Guideline No. 18 requires system change/operation/data controls; No. 7/8 require records/stock reconciliation. Cutover is not "click go-live"; it needs a rollback plan and post-go-live checks.

Acceptance checks: window; freeze; sequence; owners; Go-No-Go; rollback; parallel; go-live checks; hypercare; open items. Common gaps: no window; no freeze; no rollback; no go-live check; no hypercare.

ItemWhat to writeEvidenceCommon gap
Window/downtimeTime/impact/notificationPlanNo window
FreezeLegacy writes/interfaces/approvalsRecordNo freeze
SequenceMaster data→price/contract→inventory/opening→interfacesRunbookWrong order
OwnersRole/contact/escalationListUnclear
Go-No-GoCheckpoint/conditions/sign-offRecordNo check
RollbackConditions/steps/window/data recoveryPlanNo rollback
Go-live checksQuantity/amount/status/interfaces/reports/permissionsReportNo check
HypercareDays/response/severity/open itemsRecordNo ownership

Cutover/rollback/post-go-live are editorial; the migration plan, change management and system operations control.

How should the website page be written, and what must not be published?

Suggested sections: (1) project scope/goals/success criteria; (2) current-state inventory/data profiling; (3) mapping/cleansing/dedup rules; (4) trial migration/reconciliation/sign-off; (5) cutover/rollback/post-go-live; (6) contact window/update date. The public page explains "scope, method, quality, reconciliation, cutover, boundaries" and does not publish specific source/target system screenshots, table structures/fields, data volume/samples, supplier/material/price/bank information, interface addresses/accounts, issue details/undisclosed disputes or customer information. The English page should use consistent terms (master data, migration, cleansing, profiling, source-to-target mapping, deduplication/merge, trial migration, reconciliation, cutover, rollback, hypercare) and state the cut-off date.

Do not turn the migration page into "data migrated, system live", and do not claim "100% accurate/zero variance/no downtime" if it cannot be proven. The page should let procurement/IT/finance/internal-control/audit judge "what is migrated, how mapping/cleansing works, how reconciliation is closed, how cutover/rollback works", without exposing data and security details.

Go-live acceptance checklist

Ten checks: scope/goals/success criteria; source list/dictionary; profiling/issue list; field/value/ID mapping; cleansing/dedup/approval; trial migration/reconciliation/sign-off; cutover/rollback/Go-No-Go; go-live checks/hypercare; permissions/audit/privacy; public boundary. Each needs evidence and a review date. The pass standard is not "data was loaded", but that procurement/IT/finance/internal-control/audit can judge whether the migration is complete, mapping traceable, reconciliation closed and cutover reversible.

Before go-live, run a tabletop exercise with a real (redacted) data domain: inventory → profiling → mapping/cleansing → trial migration → reconciliation → variance fix → cutover → rollback drill → go-live checks, simulating "duplicate suppliers", "one material multiple codes", "mixed units/currencies" and "broken interface", to see whether the page and process work.

CheckPass standardEvidenceIf failed
Scope/goalsDomains/source-target/out-of-scope/success criteriaPlanAdd scope
Source list/dictionarySystem/table/field/rows/dictionaryListAdd inventory
Profiling/issuesQuality dimensions/duplicates/units/sensitive data/issue listReportAdd profiling
MappingField/value/ID/relationship/hierarchyMapping sheetAdd mapping
Cleansing/dedupRules/approval/history/auditRecordAdd approval
Trial/reconciliationRounds/full/reconciliation/variance/log/sign-offReportRe-run
Cutover/rollbackWindow/freeze/sequence/Go-No-Go/rollbackRunbookAdd plan
Go-live checksQuantity/amount/status/interfaces/reports/permissionsReportReconcile
Hypercare/auditResponse/severity/open items/log/permissionsRecordAdd operations
Public boundaryNo data/systems/suppliers/interfacesPage/permissionsTake down

The acceptance list is editorial; the migration plan, master-data policy and audit requirements control.

Who should read it, who should not, and what decisions does it support?

For procurement, IT, finance, internal-control, audit, data-governance and website teams at equipment, electronics, automotive-parts, medical-device, hardware, chemical, packaging and export manufacturers in Changzhou and nearby; also for companies handling "scope creep, unclear source data, arbitrary mapping, cleansing without approval, trial migration without reconciliation, cutover without rollback, no post-go-live ownership". Not for teams without a master-data migration/cleansing project, or that want one page to replace data-governance/IT-audit advice.

Read it if: building a migration/cleansing project page; only "data migrated"; unclear scope; source data not inventoried; mapping without rules; cleansing/merge without approval; trial migration without reconciliation; cutover without rollback; no go-live checks; missing permissions/audit. Not suitable if: treating "migration" as "export/import"; "cleansing" as "delete duplicates"; "trial" as "run a script"; "page" as "migration plan/audit conclusion". Supports: scope/goals, profiling, mapping/cleansing, trial/reconciliation, cutover/rollback/post-go-live and public-boundary self-checks.

FAQ

What is the difference between a master-data migration/cleansing project and the master-data quality page?

The master-data quality page covers ongoing domains, coding, governance, quality metrics and owner/steward; the migration/cleansing project page covers one-time delivery: scope, source inventory/profiling, source-to-target mapping, cleansing/dedup, trial migration/reconciliation, cutover/rollback/post-go-live. They complement each other: the quality page is "ongoing operations", the migration page is "phased delivery"; one cannot replace the other.

How should project scope be defined?

State the data domains (supplier/material/price/contract/category/organisation/customer/bank, etc.), source→target systems, in-scope/out-of-scope (historical years, inactive data, attachments/documents), data volume, cutover window, success criteria (quantity/amount/quality/reconciliation variance/go-live date) and roles. Scope should be verifiable and signable, avoiding "migrate everything" creep; success criteria are company-defined by business/audit requirements, not just "go live".

What should data profiling cover?

At least: source system/table/field/rows/data dictionary; completeness/uniqueness/format/range/relationships/timeliness; duplicates/aliases/one-material-multiple-codes/one-code-multiple-materials; unit/currency/tax code/organisation mapping; attachments/documents; history/inactive; sensitive data/permissions. Output an issue list/samples/impact/priority/recommendation, confirmed by the business owner/steward. Profiling is not just a script; it needs business confirmation and remediation priority.

Who sets mapping/cleansing rules, and how are they approved?

The business owner/steward sets rules, IT implements, data governance/internal control reviews; rules should be versioned, traceable and re-runnable. Field/value/ID mapping, defaults/exceptions, dedup/merge rules, missing/exception handling all need approval; merging should retain old IDs/mapping/history/audit, not delete directly. Guideline No. 18 requires system change/data controls; No. 7 requires procurement record traceability.

How is trial migration accepted?

Run multiple trial rounds (test/pre-production) covering sample/full, row/field/amount/quantity/status/relationship/attachment reconciliation; variance categories/thresholds/samples; issue log (finding/owner/fix/re-run/recheck/close); business sample confirmation (procurement/finance/warehouse/quality); sign-off/production admission. One run or "script succeeded" is not enough; you need a checkable reconciliation report and business sign-off.

How are cutover/rollback accepted?

State the cutover window/downtime, freeze (legacy writes/interfaces/approvals), sequence (master data→price/contract→inventory/opening→interfaces), owners/contacts, Go-No-Go checkpoints, rollback conditions/steps/window/data recovery, parallel/dual run (if applicable), go-live checks (quantity/amount/status/interfaces/reports/permissions) and hypercare. Cutover is not "click go-live"; it needs a rollback plan and post-go-live checks; Guideline No. 18 requires system change/operation/data controls.

Should the website publish migration methods, data volumes and systems?

Usually not specific source/target system screenshots, table structures/fields, data volume/samples, supplier/material/price/bank information, interface addresses/accounts, issue details/undisclosed disputes or customer information; it can publish project scope/method, data quality/reconciliation principles, cutover/rollback process, contact window and update date. The goal is to let customers/partners understand delivery methods, not to disclose data and security details.

One-sentence takeaway

The master-data migration/cleansing project acceptance page on a Changzhou manufacturer's website is not about "data migrated, system live"; it is about turning scope/goals/success criteria, source list/dictionary, profiling/issue list, field/value/ID mapping, cleansing/dedup/approval, trial migration/reconciliation/sign-off, cutover/rollback/Go-No-Go, go-live checks/hypercare, permissions/audit/privacy and public boundaries into a checkable list, so procurement/IT/finance/internal-control/audit can judge whether the migration is complete, mapping traceable, reconciliation closed and cutover reversible.

Research method and limitations

This article is a summary of public rules and page method, not data-governance/IT-audit advice. It uses no unpublished company source/target systems, table structures/fields, data volume/samples, supplier/material/price/bank information, interface addresses/accounts, issue details or undisclosed disputes; the tables and acceptance items are editorial and not data-governance/IT-audit conclusions. MOF Internal Control Application Guideline No. 18 (Information Systems), No. 7 (Procurement) and No. 8 (Asset Management) are public sources; the company's master-data policy, migration plan, system configuration and data standards control. This article does not decide whether any specific migration/cleansing plan is reasonable, and does not promise "100% accurate/zero variance/no downtime"; companies should set them item by item based on domains, source/target systems, data volume and cutover requirements.

Sources and basis

Current to 2026-11-10; the official pages below control.

  1. MOF Internal Control Application Guideline No. 18 — Information Systems (Cai Kuai [2010] No. 11): Linyi Finance Bureau. System development, change, operation, security and data controls; used here for system change/data controls/permissions/logs in the migration project.
  2. MOF Internal Control Application Guideline No. 7 — Procurement (Cai Kuai [2010] No. 11): Linyi Finance Bureau. Procurement records/traceability and supplier/price/contract controls; used here for supplier/material/price/contract migration and reconciliation.
  3. MOF Internal Control Application Guideline No. 8 — Asset Management (Cai Kuai [2010] No. 11): Linyi Finance Bureau. Inventory records/stock reconciliation/count; used here for inventory/opening data migration and reconciliation.
About the author

Lingyi Information Official (delivery team) handles requirements, solution and acceptance collaboration for corporate websites, brand and brochure design, smart manufacturing and AI projects. This article is public research and project-method summarisation, not data-governance/IT-audit advice; specific projects follow the company's master-data policy, migration plan, system configuration and data standards.

Turn master-data migration and cleansing into a checkable list

Bring scope, mapping, trial migration, reconciliation, cutover and rollback. We will map the migration project page into a reviewable checklist.